What is typically included in a change order?

  1. Only project completion time

  2. Changes in construction work, time, and cost

  3. Alterations in design only

  4. New contractor assignments

The correct answer is: Changes in construction work, time, and cost

A change order is an essential component of construction management that addresses adjustments to the original contract. It typically formalizes changes related to the scope of work, which may involve modifications or additions to the construction tasks. This can also include shifts in the timeline for project completion and alterations in the overall cost associated with these changes. The inclusion of changes in construction work, time, and cost allows all parties involved—such as contractors, clients, and subcontractors—to have a clear mutual understanding of the new expectations and requirements stemming from the amendments made to the original agreement. Change orders are significant because they serve to document and authorize any revisions to the project, ensuring that adjustments are agreed upon and legally recognized. Other potential choices focus on limited aspects of change orders. For instance, including only project completion time would overlook the financial implications or specific alterations to the construction work. Mentioning alterations in design only would fail to account for the logistical and financial aspects that must also be adjusted. Additionally, new contractor assignments are not typical of a change order but may be a separate contractual consideration in a project. The comprehensive nature of change orders is crucial for effective project management and collaboration.